The penetration of renewable energy sources, particularly wind energy, into power systems has been rapidly increasing in recent years. However, the integration of wind power has posed many challenges for power system operation. For instance, this type of energy source is relatively variable and unpredictable. The installation of this renewable source might require the grid to transmit power at full capacity and some transmission lines could become congested. As a result, in some operating conditions, wind power could be curtailed, which will drive up costs for system operators. One of the actions that can be taken to support the integration of the wind is using energy storage systems. In this paper, a multiperiod ac optimal power flow problem with battery energy storages (BESs) is formulated and sets of candidate buses for BES installation are identified based on an economic criterion. Tests are carried out on IEEE 14-bus and IEEE 118-bus systems to assess the robustness of storage location on system operation.

Sensitivity Analysis on Locations of Energy Storage in Power Systems With Wind Integration

BERIZZI, ALBERTO;BOVO, CRISTIAN;MOSHI, GODFREY GLADSON;NGUYEN, NHI THI AI
2016-01-01

Abstract

The penetration of renewable energy sources, particularly wind energy, into power systems has been rapidly increasing in recent years. However, the integration of wind power has posed many challenges for power system operation. For instance, this type of energy source is relatively variable and unpredictable. The installation of this renewable source might require the grid to transmit power at full capacity and some transmission lines could become congested. As a result, in some operating conditions, wind power could be curtailed, which will drive up costs for system operators. One of the actions that can be taken to support the integration of the wind is using energy storage systems. In this paper, a multiperiod ac optimal power flow problem with battery energy storages (BESs) is formulated and sets of candidate buses for BES installation are identified based on an economic criterion. Tests are carried out on IEEE 14-bus and IEEE 118-bus systems to assess the robustness of storage location on system operation.
2016
Curtailed wind; energy storage systems (ESSs); location; locational marginal price (LMPs); multiperiod; optimal power flow (OPF); production cost; sensitivity; wind integration; Control and Systems Engineering; Industrial and Manufacturing Engineering; Electrical and Electronic Engineering
File in questo prodotto:
File Dimensione Formato  
11311-1024552_Bovo.pdf

accesso aperto

: Post-Print (DRAFT o Author’s Accepted Manuscript-AAM)
Dimensione 1.72 MB
Formato Adobe PDF
1.72 MB Adobe PDF Visualizza/Apri

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11311/1024552
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 34
  • ???jsp.display-item.citation.isi??? 22
social impact